|
Back
to Contents
ANNEX
E: TOWER MAINTENANCE AND INSPECTION PROCEDURES
Owners
of towers should perform initial and periodic tower inspection and maintenance
to assure safety and to extend service life. It is recommended that major
inspections be performed, at a minimum, every 3 years for guyed towers
and every 5 years for self-supporting towers. See section 14. Ground and
aerial procedures should be performed only by authorized personnel, experienced
in climbing and tower adjusmaents.
Some
of the items listed below may apply only to initial construction of new
towers.
I. Tower
Conditions (guyed and self-supporting)
A.
Members
1.
Bent members (legs and lacing)
2.
Loose members
3.
Missing members
4.
Climbing facilities, platforms, catwalks -- all secure
5.
Loose and/or missing bolts
B.
Finish
1.
Paint and/or galvanizing condition
2.
Rust and/or corrosion conditions
3.
FAA or ICAO color marking conditions
4.
Water collection in members (to be remedied, e.g., unplug drain holes,
etc.)
C.
Lighting
1.
Conduit, junction boxes, and fasteners weather tight and secure
2.
Drains and vents open
3.
Wiring condition
4.
Controllers functioning
a.
Flasher
b. Photo control
c. Alarms
5.
Light lenses
6.
Bulb condition (Option: change all bulbs at one time)
D.
Grounding
1.
Connections checked and secure
2.
Corrosion observed and remedied
3.
Lightning protection secure (as required)
E.
Tower Base Foundation
1.
Ground Conditions
a.
Settlements or movements
b. Erosion
c. Site condition (standing water, drainage, trees, etc.)
2.
Base condition
a.
Nuts and lock nuts tight
b. Grout condition
3.
Concrete Condition
a.
Cracking, spalling, or splitting
b. Chipped or broken concrete
c. Honeycombing
d. Low spots to collect moisture
e. Anchor-bolt corrosion
F.
Tower Assembly Pro£fie (See Figures E1 and E2)
1.
Antennas and feedlines (each)
a.
Frequency
b. Elevation
c. Type
d. Size
e. Manufacturer
f. Connectors and hangers
2.
Optional appurtenances (walkways, platforms, sensors, floodlights,
etc.)
a.
Elevation
b. Arrangement
c. Drawings or sketches
3.
Foundation and anchors
a.
Plan
b. Elevations (relative or mae)
c. Size
d. Depths
e. Soil type (if known or necessary)
G.
Tower Alignment (See Figures E3, E6, and E7)
1.
Tower Plumb and Twist (See 6.1.2.1 and 6.1.2.2)
H.
Insulators (As Required)
1.
Insulator Condition
a.
Cracking and chipping
b. Cleanliness of insulators
c. Spark gaps set properly
d. Isolation transformer condition
e. Bolts and connections secure
f. Manufacturer type and part numbers for future replacements
II.
Guyed Towers
A.
Anchors
1.
Settlement, movement or earth cracks
2.
Backffil heaped over concrete for water shedding
3.
Anchor rod condition below earth (Maintain required structural capacity
of anchor during exploration, inspection and maintenance. Attachment
to temporary anchorage may be required.)
4.
Corrosion control measures (galvanizing, coatings, concrete encasement,
cathodic protection systems, etc., refer to Annex J.)
5.
Grounding (Paragraph I-D)
6.
Anchor head clear of earth
B.
Tower Guys (see Figures E4 and E5)
1.
Strand
a.
Type (lx7 EHS, lx19 bridge Strand, etc.)
b. Size
c. Breaking strength
d. Elevation
e. Condition (corrosion, breaks, nicks, kinks, etc.)
2.
Guy Hardware
3.
Elements
a.
Bent, broken, cracked or bullet damaged
b. Loose
c. Missing
d. Loose and/or missing fasteners
4.
Corrosion condition
5.
Radomes and/or cover conditions
B.
Feed Lines (waveguide, coax, etc.)
1.
Hangers and supports
a.
Condition
b. Quality
c. Corrosion condition
2.
Flanges and seals (check integrity)
3.
Line Condition
a.
Dents
b. Abrasions
c. Holes
d. Leaks
e. Jacket condition
4.
Grounds
a.
Top ground strap bonded both ends
b. Bottom ground strap bonded both ends
5.
Feedline support (ice shields)
a.
Properly attached
b. Loose and/or missing bolts
c. Members straight and undamaged
TOWER
ELEVATION
Show the following:
| --
Tower Height above ground |
--
Location of feed lines |
| --
Location of antennas |
--
Location of platforms, ladders, etc. |
Click
for Figure E1
PLOT
PLAN
Show the following:
| --
Tower layout relative to North |
--
Access roads and buildings |
| --
Anchors and assign letter designation |
--
Power lines and poles |
| --
Relative or true anchor and base elevations |
|
Click
for Figure E2
TOWER
LEG VERTICAL ALIGNMENT
1.
Check with transit. Two transit setups are required. Line transit parallel
to one face and center on leg. Second setup should be at 90° on same leg.
Show on sketch below the locations used for transit setup. Indicate North.
Click
for Table E8
Approximate wind speed
during measurements mph
Note:
This procedure is not sufficient to determine both twist and out of plumb.
Click
for Figure E4
Click
for Figure E5
Click
for Figure E6
Click
for Figure E7
IV. Methods For Measuring
Guy Initial Tensions
There are two basic methods of measuring guy initial tensions in the field:
the direct method
and the indirect method.
A. The Direct Method
(see Figure E8)
A
dynamometer (load cell) with a length adjustment device, such as
a come-along, is attached to the guy system by clamping onto the
guy just above the turnbuckle and onto the anchor shaft below the
turnbuckle, thus making the turnbuckle redundant.
The
come-along is then tightened until the original turnbuckle begins
to slacken. At this point the dynamometer carries all of the guy
load to the anchor, and the guy tension may be read direcfiy off
the dynamometer dial.
One
may use this method to set the correct tension by adjusting the
come-along until the proper tension is read on the dynamometer.
Two control points are marked, one above the clamping point on the
guy and one on the anchor shaft, and the control length is measured.
The dynamometer and come-along are then removed, and the original
turnbuckle is adjusted to maintain the control length previously
measured.
B. The Indirect Method
(see Figures E8 and E9)
There
are two common techniques for the indirect measurement of guy initial
tensions: the pulse or swing method (vibration) (Figure E8) and
the tangent intercept or sag method (geometry) (Figure E9).
1.
The Pulse Method (see Figures E8 and E10)
One
sharp jerk is applied to the guy cable near its connection to
the anchor causing a pulse or wave to travel up and down the cable.
On the first return of the pulse to the lower end of the guy cable
the stop watch is started. A number of returns of the pulse to
the anchor are then timed, and the guy tension is calculated from
the following equations:

in which (see Figure
E10)
TA = Guy tension at anchor (lb) .....
TM = Guy tension at mid-guy (lb)
W = Total weight of guy, including insulators, etc. (lb)
L = Guy chord length (ft)

V = Vertical distance
from guy attachment on tower to guy attachment at anchor (ft)
H = Horizontal distance from guy attachment on tower to guy attachment
at anchor
fit)
N = Number of pulses or swings counted in P seconds
P - Period of time measured for N pulses or swings (s)
Instead of creating a pulse that travels up and down the guy, one may
achieve the
same result by causing the guy cable to swing freely from side to side
while timing N
complete swings. The formulas given above will also apply for this approach.
2. The Tangent Intercept Method (see Figure E9)
A line of sight is established which is tangential to the guy cable near
the anchor end
and which intersects the tower leg a distance (tangent intercept) below
the guy
attachment point on the mast. This tangent intercept distance is either
measured or
estimated and the tension is calculated from the following equation:

in
which
C
= Distance from guy attachment on tower to the center of gravity of
the weight W (ft)
I =
The tangent intercept (ft)
ff
the weight is uniformly distributed along the guy cable, C will be approximately
equal to 1-I/2. If the weight is not uniformly disWibuted, the guy may
be subdivided into n segments and the following equation may be used:

in
which

Wi =
Weight of segment i (lb)
Ci
= Distance from the guy attachment on the tower to the center of gravity
of segment i (ft)
If the
intercept is difficult to establish, one may use the guy slope at the
anchor end with the following equation:

in which
cz =
Guy angle at the anchor (see Figure E9)
Note
that

and that

and that
WC in equation (7) may be replaced with S, as was done in equation (5).
Click
for Figure E8
Click
for Figure E9
Click
for Figure E10
Back
to Contents
|